On Alma Real, the Library Opens Longer Just as the Park Next Door Closes

"There's no denying construction is tough, and a year-plus of construction at the park is going to have bumps and hurdles," Park Advisory Board President Andy Starrels said at the board's October 15 meeting, as reported by the Palisadian-Post.

He was talking about 851 Alma Real Drive. Next door, at 861, the Palisades Branch Library is moving the other way. Its new, longer hours started on Tuesday, November 3, and its November program fills the month. The two addresses have long worked as one civic block. This winter they split. The library takes on more of the block's public use while the Recreation Center shrinks to tennis and bocce, and the timelines don't come back together until spring 2027 at the earliest.

Two addresses, ten numbers apart

Reconstruction of the Palisades Recreation Center began October 26 with utility work and site clearing. The bigger closures start in mid-November. Here is where each part of the block stands this week and where it is headed.

Facility As of this week Coming up
Palisades Branch Library, 861 Alma Real Open Tuesday through Saturday on expanded hours November programs run through Nov. 21
Recreation Center parking lots Open Both lots close in mid-November
Playground and basketball courts Open Close in mid-November
Ball fields Open Close in mid-November; target return March 2027
Palisades Tennis Center Resurfaced courts back in play Stays open "as long as possible"
Bocce courts Open Stays open "as long as possible"

The mid-November closures also take in the maintenance yard. Tennis and bocce are the only outdoor uses the project team has said will stay open into the build, and only for as long as the work allows.

What the library added, and when

The branch is now open from noon to 5:30 p.m. on Tuesdays and Thursdays, and from 10 a.m. to 5:30 p.m. on Wednesdays, Fridays and Saturdays. It stays closed Sundays and Mondays. The Friends of the Palisades Library welcomed the change and are still pressing the Los Angeles Public Library system to add Tuesday and Thursday mornings. That makes three mornings a week on the block, against five afternoons.

Most of the November calendar takes place in the branch's Green Bungalow or online. Baby and Toddler Storytime came back on November 4. Here is what's left this month:

  • Saturday, November 7, 1:30 to 2:30 p.m. Musician Wendy Hersh leads "Where the Wild Rhythms Are," an interactive family music concert.
  • Tuesday, November 10, 1:30 to 2:30 p.m. The Mysterious Book Club discusses Lisa See's "Daughters of the Sun and Moon," and See joins virtually.
  • Tuesday, November 17, 12:30 to 3:30 p.m. Duplicate bridge returns to the Green Bungalow. It's aimed at intermediate players, who are encouraged to bring a partner.
  • Saturday, November 21, 10 a.m. A virtual discussion of James Bird's novel "Wolf Club" for students in grades four through seven.
  • Saturday, November 21, 1:30 to 3 p.m. "L.A. Made: Book and Paper Arts," a hands-on workshop led by Laurel Koss covering Japanese bookbinding, accordion and flag books, papermaking, collage and printmaking.

Several of these used to have a natural partner across the lot. A toddler storytime used to end at the playground, and a Saturday family concert used to share the morning with ball games. As of mid-November, the library programs are the ones still running on the block. Updates to the schedule are posted on the Los Angeles Public Library's Palisades branch page.

What closes, and where the programs already went

The Recreation Center's programs didn't wait for the fencing. A July Palisadian-Post report said local basketball leagues, flag football, senior kickball and crocheting classes had moved for now to Rustic Canyon Park and Penmar Park. A June report from the project's community webinar said Recreation Center staff had moved to a satellite office at Rustic Canyon. It also said summer basketball divisions were assigned to Rustic Canyon and Palisades High School, and flag football was going to Penmar Recreation Center.

At the time of that June webinar, baseball was expected to stay put through construction. The October closure plan changes that and puts the ball fields inside the fenced area starting mid-November.

The tennis courts are the exception. Renovation at the Palisades Tennis Center was close to done in October. Two upper courts had reopened with new surfacing and fencing, and board member Mike Tomas said the last two were scheduled for October 19. "If that's the case and we're on target, that means all eight courts will be available for play," Tomas said, according to the Palisadian-Post. The courts don't have new lighting yet, and the center is still working on plans for a new clubhouse.

The first piece back is the baseball diamond

Project leaders expect the ball fields and the lower parking lot to reopen in time for baseball season in March 2027. Starrels added that "those dates will be constantly fine-tuned as they get further feedback from subcontractors and as weather conditions affect the build." Nick Geller, managing director of Steadfast LA, said the team would try to rebuild the fields in time for the Pacific Palisades Baseball Association's March 2027 season.

The rest takes longer. At the September groundbreaking, Rick Caruso gave a 12- to 15-month estimate for the full build. The July report put it at up to 18 months. Counting from the October 26 start, the earliest estimate lands in late 2027.

What comes back is bigger than what left. The city's January 2026 board report describes a roughly 28,000-square-foot building replacing the two old recreation buildings, which together came to about 18,000 square feet. The new building will hold:

  1. Two indoor basketball courts with bleachers
  2. Two indoor pickleball courts
  3. A lobby and a multipurpose room
  4. Offices, storage and restrooms

Outside, the site plan moves and rebuilds the playground and outdoor basketball courts. It adds an outdoor meeting area, shaded community pods, a multipurpose field, terraced seating, better paths and lighting, and a repaired parking area and access road. Renderings shown in June go further. They include a two-level sloped playground with embankment slides, a U10 soccer field, two lighted outdoor basketball courts, a central "Pali Hub," a Veterans Garden, bocce improvements, EV and ADA parking, and a stormwater cistern. Gensler is designing the main building and SWA Group the landscape.

Who is paying for it

The city's January report names PPRC Development Project, LLC as the donor and values the proposed gift of the center and its improvements at about $40 million. Under the term sheet, the donor pays for design, permitting, construction and landscaping and runs the fundraising. Construction could begin only once committed funding reached at least half of two things combined: the budget for building the whole project, and the cost of the donor's other obligations under the final agreement.

At the groundbreaking, as covered by the Palisadian-Post, Caruso said "$40 million has been committed to begin construction immediately," with fundraising continuing for the remaining pieces. He also said, "There will not be a dime of taxpayer money put into this park." The partnership brings together the City, Steadfast LA and LA Strong Sports, the organization led by Lakers coach JJ Redick. Steadfast says local community groups were involved in the early design.

That fundraising condition helps explain the order of work. The ball fields return first because a baseball season has a fixed opening day. The building comes later.

The block's calendar from here

  1. November 3: Expanded library hours began.
  2. November 7, 10, 17 and 21: The remaining library programs, listed above.
  3. Mid-November: Both Recreation Center parking lots, the playground, the basketball courts, the ball fields and the maintenance yard close. Tennis and bocce stay open as long as possible.
  4. March 2027: Target for the ball fields and lower parking lot to reopen for baseball season.
  5. Late 2027 or later: The new recreation building and the rest of the park, based on the 12- to 18-month estimates given during 2026.

Starrels asked residents to keep telling the Park Advisory Board how the construction period is going. "Let us know what's working and not," he said. "We'll pass it along to Steadfast. They want to be engaged."

At Carmody Real Estate, we follow the Palisades rebuild block by block, from library hours to opening day for the ball fields. If you want to talk about how projects like the Alma Real rebuild fit into your own plans in the neighborhood, Contact Us.

Work With Us

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact us today.

Follow Me on Instagram